The NYC Department of Buildings (DOB) issued updated guidance on essential and non-essential construcion on April 15. Public and private school construction projects are now deemed essential, and Marymount's building project was confirmed as essential by the DOB on April 23. To facilitate the start of work under the current guidelines, contractors will follow safety protocols for social distancing onsite, augmented PPE, additional cleaning of surfaces, etc.
Inquiries:
646-218-8119 construction@marymountnyc.org
Week of July 17
MEP:
SPK - misc punch list work
Mechanical - controls, installing air outlets, commission cooling system, punch list work, theater rough
Plumbing - punch list work
Electrical - theater wire pulls and gear, punch list work
Low voltage - terminating and testing devices, MDF room, wireless door hardware
Drywall - central stair sheetrock and taping, punch list work, theater operations, gym railing framing Painting - topcoats throughout Misc Metal - gym railings Millwork - central stair millwork, lobby columns and ceiling ribs installation Vertical Transportation - car 3 work, ADA lift CMU Work - miscellaneous
Exterior Walls
exterior stone on 97th & 98th Streets
courtyard work, trees, and irrigation
entrance pavers on 97th Street
Saturday, July 22 (9:00 a.m. - 5:00 p.m.): continuation of scope above
Week of July 24
MEP:
SPK - misc punch list work
Mechanical - controls, installing air outlets, commission cooling system, punch list work, theater rough
Plumbing - punch list work
Electrical - theater wire pulls and gear, punch list work
Low voltage - terminating and testing devices, MDF room, wireless door hardware
Drywall - central stair taping, punch list work, theater operations, gym railing framing Painting - topcoats throughout Millwork - central stair millwork, lobby columns and ceiling rib installations Vertical Transportation - car 3 work, ADA lift CMU Work - miscellaneous
Exterior Walls
exterior stone on 98th Street
courtyard work, pavers
new curbs and sidewalk on 98th Street
Saturday, July 29 (9:00 a.m. - 5:00 p.m.): continuation of scope above
New York Department of Building standard work hours are Monday through Friday from 7:00 a.m. to 6:00 p.m. Exact timing of construction schedule is dependent upon weather conditions and may be subject to change.
We hope to keep to this expected schedule but will keep you updated if there are any unexpected delays in our plans. Check back to this page for detailed updates on the construction timeline as they become available.